You need to push a change to 800 switches with automation. How do you make it safe?

Show the answer

Say this first

I treat it as a staged rollout. Pre-checks gate each device, a dry run diff is reviewed, and the change goes to one or two canary devices first, then a small batch, then the rest, stopping on the first failure. Where the platform has it I use confirmed commit so a change that cuts my access rolls itself back. Post-checks run after every batch, and I keep out-of-band access, a tested rollback and a kill switch.

Go deeper

Before

  • Peer-reviewed merge request with a dry run diff for a sample of device types.
  • Tested on a lab device with the same platform and release.
  • Pre-checks: device reachable, healthy, config matches the expected baseline. Skip and report devices that fail.
  • Rollback written and tested, not just "re-run the old playbook".

During

YAML
- name: Push new AAA config
  hosts: access_switches
  gather_facts: false
  serial: [1, 5, "10%", "25%"]
  max_fail_percentage: 0
  tasks:
    - name: Apply template
      cisco.ios.ios_config:
        src: aaa.j2
        save_when: modified

serial grows the batches, and max_fail_percentage: 0 stops the rollout as soon as any device in a batch fails. forks limits how many devices are touched at once, which also protects TACACS servers.

Safety nets per platform

  • Junos and NETCONF candidate: commit confirmed with a few minutes timeout.
  • IOS-XE with archive configured: configure terminal revert timer then configure confirm.
  • Changes that touch management access (AAA, ACLs on vty, management VRF) go last and slowest.

After

Post-checks per batch, compare with pre-checks, then a final report: changed, unchanged, failed, skipped.

Traps

  • Running against all 800 at once because "it worked in the lab".
  • Changing AAA or management ACLs without a confirmed-commit or console fallback, and locking yourself out everywhere.